Aubrick

Aubrick

Client
Aubrick
Location
Brooklin, São Paulo, SP

Easy won the bid to build the new Aubrick school building in Brooklin, São Paulo, and carried out the entire project starting from a metal structure already erected on the site, with design by Laranja Lima Arquitetura. The 4,000 sqm were built in about eight months, with a multi-sport court on the roof, as a Turnkey delivery. The building opened in January 2015.

What was the scope of the Aubrick project?

Aubrick had the design ready and the site with the metal structure in place. Easy carried out everything else:

  • completion of the metal structure, with fire protection;
  • steel deck slabs;
  • closing in the masonry;
  • all infrastructure: electrical, fire fighting and detection;
  • new window frames and wall and floor coverings;
  • installation of the elevators;
  • renovation of an outbuilding on the site.

How do you build a court on the roof of a school?

Part of the sports program was placed at the top of the building, with a multi-sport court on the roof. The slab received leveling, waterproofing with asphalt membrane, a separation layer and a drainage layer before the sports flooring, protecting the classrooms below.

What was the main challenge?

The opening date was set. The project had to take the building from a metal structure to a functioning school within that deadline, with installations, enclosures and finishes carried out in sequence until delivery.

What was the contracting model?

Construction project with Turnkey delivery. The architectural design already existed, by Laranja Lima Arquitetura, and Easy won the bid to build the building.

What was the result of the project?

The project was delivered on time, and the school opened the new building on the planned date, in January 2015, with the school’s satisfaction.

After it, Aubrick hired Easy again for two more projects, at other units, and is now a repeat client.

See other projects in the Educational segment.

Frequently asked questions

What stage was the building at when Easy came in?
There was only the metal structure on the site. Easy completed the structure and carried out everything else, from masonry to the installation of the elevators.
What was the project area?
4,000 sqm.
How long did the project take?
About eight months, delivered on time for the opening of the new building in January 2015.
How can a court sit on the roof of a school?
The slab receives leveling, waterproofing with asphalt membrane, a separation layer and a drainage layer before the sports flooring, which protects the classrooms below.
Did Aubrick hire Easy again?
Yes. After the main building, Easy carried out two more projects at other units. Aubrick is now a repeat client of Easy.

Aubrick

Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs
Aubrick school classroom in São Paulo with white tables and green chairs