- Infinity building, Faria Lima area, São Paulo, SP
- Area
- more than 5,000 sqm, across four floors
Easy was responsible for Credit Suisse’s build-out in Brazil, in the Infinity building, in the Faria Lima area of São Paulo. It covered four floors and more than 5,000 sqm, completed in four months, with four engineering teams working at the same time.
What was the scope of the Credit Suisse project?
Easy built the office of Credit Suisse, an international investment bank, on four floors of the Infinity building, totaling more than 5,000 sqm. The design has a great deal of joinery finishing and a great deal of marble. The project included opening slabs and installing stairs between floors, at the standard of an international investment bank.
Why is this project relevant?
The Infinity building is an iconic tower in the Faria Lima area, housing several companies. The Credit Suisse works were the first projects carried out in the building.
How was the project organized?
The work was simultaneous on the four floors, with four engineering teams working at the same time. It was the way to build out more than 5,000 sqm within a four-month schedule.
What was the contract model?
It was a construction-only contract, not Design & Build. Easy was responsible for execution.
What was the result of the project?
The project was delivered on time and to the expected quality.
Frequently asked questions
- What was the area of the Credit Suisse project?
- More than 5,000 sqm, across four floors.
- How long did the project take?
- Four months.
- Where is the office?
- In the Infinity building, in the Faria Lima area, in São Paulo.
- How many teams worked on the project?
- Four engineering teams, working at the same time.
- Did the project involve opening slabs?
- Yes, with the installation of stairs between floors.