Dufry

Dufry

Client
Dufry
Location
Terminal 3, Guarulhos Airport, SP

Easy built the Dufry store at Terminal 3 of Guarulhos International Airport, with about 4,500 sqm. The work was carried out at the same time as the terminal’s own construction, to open in time for the 2014 World Cup, on the airport’s airside, with all the logistics and documentation required. The design came from outside Brazil and was adapted to local conditions by Easy, with Turnkey delivery. The site ran 24 hours a day, in three shifts, with about 600 professionals, and was delivered about a month ahead of schedule.

What was the scope of the Dufry project?

Easy built the Dufry store at Guarulhos Terminal 3, with about 4,500 sqm. It was Easy’s largest project for Dufry.

The design was developed outside Brazil. Easy handled the localization, adapting specifications and solutions for execution in the country.

What were the project’s challenges?

  • Built alongside the terminal: the store was built at the same time as Terminal 3 itself, with the opening deadline set by the 2014 World Cup.
  • Airside: the site was beyond the Federal Police checkpoint, in the airport’s restricted area. This requires specific logistics and full documentation for crew and material access. Any tool not on the list cleared by the Federal Police required a new request, with a 48-hour wait.
  • International design: the specifications that came from abroad had to be adapted to the Brazilian market.

How did Easy meet the deadline?

The site ran 24 hours a day, in three shifts, with about 600 professionals. The flooring was carried out in four simultaneous fronts. With this organization, the store was delivered about a month ahead of schedule.

What was the contracting model?

Easy built the international design, already adapted to local conditions, with Turnkey delivery.

What was the result?

The store was ready about a month ahead of schedule, in time for the opening of Terminal 3 for the 2014 World Cup, with a satisfied client.

Dufry is a portfolio client of Easy, with several projects at the airport. Besides Terminal 3, Easy built the Terminal 2 departures project, other renovations for Dufry and stores of the group’s brands, such as Luxottica, Ferragamo, Gap and MAC, all inside the airport.

See other projects in the Commercial segment.

Frequently asked questions

Where is the store?
At Terminal 3 of Guarulhos International Airport.
What was the project area?
About 4,500 sqm.
Why was the project special?
It was built at the same time as Terminal 3 itself, to open in time for the 2014 World Cup.
How did the project meet the World Cup deadline?
With execution 24 hours a day, in three shifts, about 600 professionals and four flooring fronts. The store was delivered about a month ahead of schedule.
What is it like to build on the airside of an airport?
The site is beyond the Federal Police checkpoint, in the restricted area. Crews and materials enter with dedicated logistics and all the documentation required by the airport.

Dufry

Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport
Dufry store at Terminal 3 of Guarulhos International Airport